Project Information

📍 Location: No. 131 Co Bac Street, Cau Ong Lanh Ward, District 1, Ho Chi Minh City, Vietnam
📐 Scale: Grade III structure; site area of ​​nearly 6,623.0 m²
🎨 Investor: The Construction Investment Management Board of District 1
⏱️ Time of execution: 24 mouths

📋 Implementation stages:

  • ✔️ Stage 1: Dossier for fire safety design approval.
  • ✔️ Stage 2: Rough installation (fire alarm wiring, emergency exit lights, fire-fighting piping, and lightning protection grounding pits).
  • ✔️ Stage 3: Complete equipment installation. Technical acceptance.
  • ✔️ Stage 4: Fire safety acceptance and licensing; Handover, operational guidance, and commissioning of the facility.

Project Information 📍 Location: No. 131 Co Bac Street, Cau Ong Lanh Ward, District 1, Ho Chi Minh City, Vietnam 📐 Scale: Grade III structure; site area of ​​nearly 6,623.0 m² 🎨 Investor: The Construction Investment Management Board of District 1 ⏱️ Time of execution: 24 mouths 📋 Implementation stages: ✔️ Stage 1: Dossier for…